"The City Council has not received any claim by the hospital's construction company which has not signed any contract" (12/05/2010)

In relation to statements made by the managing director of SMS, José Antonio Alarcón, relating to an alleged claim by the builder of the Hospital del Mar Menor, the municipality of San Javier for the delay in the power envelope of the building Mayor of San Javier, Pepa Garcia states:

First, the City of San Javier has not signed any contract with the Hospital's construction company and therefore has not filed or may file a claim against the City.

Secondly, the power issue is solved by the City through an agreement signed on 12 April with Iberdrola for the electrical coupling, which according to information received by the government team will be operational next week.

Therefore, no interest is understood both by the regional administration in blame, just now, the municipality of San Javier a possible delay in opening the hospital.

Third, it is incomprehensible and unacceptable to be the managing director of SMS, a political appointee, who announced the petition of four million euros as a responsibility by a private company to the City of San Javier, when even those responsible for the company refused to confirm such extremes, especially when there is no contractual relationship between that company and City Hall.

The entrances to the hospital, including the pipe line to carry the electricity to the hospital in the coming days, once the connection of it by Iberdrola, are fully completed.

Source: Ayuntamiento de San Javier

Notice
UNE-EN ISO 9001:2000 - ER-0131/2006 Región de Murcia
© 2024 Alamo Networks S.L. - C/Alamo 8, 30850 Totana (Murcia) Privacy policy - Legal notice - Cookies
Este sitio web utiliza cookies para facilitar y mejorar la navegación. Si continúas navegando, consideramos que aceptas su uso. Más información